Throughout the month there will be material deliveries. We will stay within the permitted traffic lanes for these deliveries.
We will be performing street trenching for utilities on Harriet St., Bryant St. and Boardman St. parking lanes. We will have traffic control in place per approved special traffic permits.
We will stage a crane on Bryant St. for hoisting roof equipment in early February. We will have traffic control in place per approved special traffic permits.
We will be performing work on the exterior scaffolding throughout the month, which will produce general construction noise.