• Throughout the month there will be material deliveries. We will stay within the permitted traffic lanes for these deliveries. 
  • We will be performing work on the exterior scaffolding throughout the month, which will produce general construction noise. 
  • We will be dismantling scaffold on Boardman Place elevation in mid-June.  
  • We will be beginning excavation of utility work behind the building (opposite of Bryant St.) in early June, which may require some trucks to stage and exit on Harriet St. 
  • Towards the end of June, concrete trucks will be staged on Harriet St. to access behind the building. 
  • We will set up a mobile crane on Bryant St. on 6/14 to hoist equipment to the roof. This will require temporary lane closures that we have a permit for.