The period for setting factory-built housing modules has been set to begin Sunday May 2nd. In preparation of setting the modular units, the mobile cranes have been set up on site and will remain there until all the modules are set into place.  The set will occur each evening, Sunday to Friday morning, from approximately 10pm to 6am each night. The SFMTA have let us know that they will not approve setting to start at 10 p.m. on nights when SF Giants games are in town.  Therefore, setting will start the earliest 12:00 A.M. on nights when the SF Giants games are in town.  Trucks will be present on Stevenson St during these periods to deliver the mods. We will still be working normal daytime hours during the workweek as well.

Utility work will continue at the intersection of 6th St and Jessie St and the south side of Jessie St. The work will be performed during the daytime through the end of May. This will involve a small excavator excavating a trench along Jessie St, Monday to Friday. The utility contractor will gladly relocate any construction vehicles or equipment in order for local traffic to proceed through. All excavation locations will be covered with plates while the work is not being performed.