The mod setting period will continue through June. The mobile cranes set up on site and will remain there until all the modules are set into place. Additionally, another mobile crane will be set up on Stevenson Street to set the final mods on the Stevenson Street exterior. Through-traffic on Stevenson Street during normal daytime hours (not during the scheduled mod set) will be allowed. The set will occur each evening, Sunday to Friday morning, from approximately 10pm to 6am each night. The SFMTA have let us know that they will not approve the ‚Äčtransporting of modules to start at 10 p.m. on nights when SF Giants have night games.  Therefore, transporting of modules impacting the traffic on 7th St and Stevenson will start at 12:00 A.M. on nights when the SF Giants games are in town.  Trucks will be present on Stevenson St during these periods to deliver the mods. We will still be working normal daytime hours during the workweek as well. Utility work will continue at the intersection of 6th St and Jessie St and the south side of Jessie St. The work will be performed during the daytime through the end of June. This will involve a small excavator excavating a trench along Jessie St, Monday to Friday. The utility contractor will gladly relocate any construction vehicles or equipment in order for local traffic to proceed through. All excavation locations will be covered with plates while the work is not being performed.