Concrete pours will continue through November. The Level 2 Podium along Stevenson Street will be poured on 11/10/20 and the Level 2 podium along Mission Street will be poured on 11/21/20. This will require closure of Stevenson Street to through-traffic on 11/10/20 and closure of the Northern traffic lane of Mission St on 11/21/20 during the day. This will also generate typical construction noise. We will continue to implement procedures to mitigate dust. Currently, mod set is estimated to begin on 1/3/21.