Out Blog

Upcoming activities: January 2021

January 1, 2021 833 Bryant
  • Throughout the month there will be material deliveries. We will stay within the permitted traffic lanes for these deliveries.
  • We will be performing street trenching for utilities across Bryant St. (near Boardman Place intersection). We will have traffic control in place per approved special traffic permits.
  • We will be waterproofing the exterior elevations, which could produce an odor.
  • We will be performing work on the exterior scaffolding throughout the month, which will produce general construction noise.

Upcoming Activities: December 2020

December 1, 2020 1064 Mission

Concrete pours will continue through December. Concrete pours from Stevenson St are scheduled for December 1st, 2nd, 18th and 30th. Stevenson Street will be closed during the day to through traffic for the duration of these pours. This will also generate typical construction noise. Currently, mod set is estimated to begin on 1/7/21.

Upcoming activities: December 2020

December 1, 2020 833 Bryant
  • Throughout the month there will be material deliveries. We will stay within the permitted traffic lanes for these deliveries.
  • We will be installing the roof throughout the month, which could produce an odor.
  • We will begin waterproofing the exterior elevations the 3rd week of December, which could produce an odor.
  • We will be performing work on the exterior scaffolding throughout the month, which will produce general construction noise.

Upcoming Activities: November 2020

November 1, 2020 1064 Mission

Concrete pours will continue through November. The Level 2 Podium along Stevenson Street will be poured on 11/10/20 and the Level 2 podium along Mission Street will be poured on 11/21/20. This will require closure of Stevenson Street to through-traffic on 11/10/20 and closure of the Northern traffic lane of Mission St on 11/21/20 during the day. This will also generate typical construction noise. We will continue to implement procedures to mitigate dust. Currently, mod set is estimated to begin on 1/3/21.

Upcoming Activities: November 2020

November 1, 2020 833 Bryant
  • Throughout the month there will be material deliveries. We will stay within the permitted traffic lanes for these deliveries.
  • The 3rd week of November, a crane will be set up for 1-day to hoist materials to the roof. This will require an additional traffic lane on Bryant St. temporarily.
  • The 3rd week of November and through mid-December, we will be installing the roof which could produce an odor.
  • We will be performing work on the roof throughout the month, which will produce general construction noise.